|
|
|
Goleta Beach Master Planning
Working Group
March 4, 2004
MINUTES
|
|
1. |
Welcome and Introductions
Overview of paperwork given to
the group: policies, references. |
|
2. |
Public Comments
No public comments. |
|
3. |
Minutes from
February 19th Meeting |
|
|
There were no comments or
changes to the minutes for the last meeting |
|
4. |
Updates |
|
|
-
BEACON: Karl Treiberg
distributed a spreadsheet on the costs of the project. This spreadsheet has
been put on the website. For the last round of sand deposited, the total
dumped was 18,589 yards at a cost of $150,963 ($8.58/yd). Due to the large
swells in the previous week, half of this sand is gone. If the deposited
sand had not been there, the park would have continued to erode. The sand is
clearly moving down coast, and will show up in the cross sections during
monitoring. The cost does not include permitting, engineering or monitoring.
A comment was made about dyeing the sand to see where it goes. This is
expensive, however.
|
Q: |
Does
the harbor dredge regularly? |
|
|
-
The Corp of
Engineers dredges the harbor, but does not deposit the sand out
far enough so 7% of this sand ends up at West Beach, around 15,000
yards of sand would be available yearly. But additional funds
would be needed to truck sand every year. In the BEACON
Demonstration project trucking was more cost effective than
barging the sand, because BEACON used contracted Flood Control
truckers.
-
County Parks: The
Parks staff monitors at several (6) different measuring points.
This monitoring shows where sand was gained and lost. The
emergency revetment is still covered. They submitted a plan for
the revetment to the Coastal Conservancy a month ago, but have not
heard back from them. State Lands are also interested in
conducting a survey.
|
|
Q: |
Are
documents available such as the Carrying Capacity Study (CCS), as
references for working group? |
| |
|
|
|
|
5. |
Possible Utility Line Relocation |
|
|
Goleta Sanitary District
-
They have a 36-inch pipe
one mile offshore parallel to Goleta pier, perpendicular to the
beach. The pier extends about 1500 feet. This pipe discharges
wastewater from the treatment plan, and is the only pipe for this.
-
Sewer access: There is a
concrete vault west of the parking lot, at the west end of the
restaurant, parallel to the restrooms. This is the facility that
could be at risk. The cost to open it up is $250,000, and to move it
back would cost at least $500,000.
|
Southern California Gas Company
-
They have a 36-inch pipe
one mile offshore parallel to Goleta pier, perpendicular to the beach.
The pier extends about 1500 feet. This pipe discharges wastewater from
the treatment plan, and is the only pipe for this.
-
Sewer access: There is a
concrete vault west of the parking lot, at the west end of the
restaurant, parallel to the restrooms. This is the facility that could
be at risk. The cost to open it up is $250,000, and to move it back
would cost at least $500,000.
|
-
The pipe under Goleta Beach (the
Miller-one well) runs into the main storage, with pipes connecting to
outside areas like Ventura. The pressure of the pipes is 500-1000 lbs.
Nothing is connected to this line; it is just used for transferring to
the main storage center.
-
Potential cost to move the pipe: They have
no right of way to move the pipe. A lot of the pipe exists in the
Cal-Trans right of way. The biggest cost is in the permitting/EIR
process. For example, with the Carpinteria custody transfer station; $
1 million was spent over three years for the EIR process.
-
· Digging a new pipeline (construction
only): $500-800,000.
|
|
Q: |
Who is the easement with? |
|
A: |
Unknown
|
|
Q: |
Are there emergency plans
for routing? |
|
A; |
The California
Utilities Commission governs them. With landslides, they were able to
get permits to run the pipe above the ground. There is no emergency
line.
|
|
Q: |
Are there any emergency
easements? |
|
A: |
· With an earthquake, for
example, they can maintain service due to the looping nature of the
pipeline, but pressure would not be maintained. In summary then, this
is a main storage area and transmission lines to customers are not
impacted.
|
|
Q: |
How deep is the pipe? |
|
A: |
· Unknown, Tim Mahoney
will find out.
|
|
Q: |
If the pipe is damaged (in
an emergency), who pays? |
|
A: |
Price of gas is set
by the PUC, so cost will be passed on to the customer.
|
Goleta Water District
|
Q: |
Is there an emergency
plan? |
|
A: |
The valves are shut
off. Since this water is used primarily for irrigation, this is an
interruptible water supply. However in the summer customers like
the Golf Course get upset at the lack of water for maintaining
their greens. Post Office on Hollister uses this entirely for
their toilets.
|
|
Q: |
Is there an easement
with Cal-Trans? |
|
A: |
· It is possible to
use their right of way, but must go through the permit process.
|
|
Goleta Beach uses the
water for the restroom in the middle of the park, as well as for
irrigation.
|
Other questions and comments
regarding utilities:
-
They must be able to
raise money to move the lines
-
Sale of certificates
of participation?
-
How long have pipes
existed? What are the maintenance schedules?
-
The Gas Company just
cleaned the pipes, and the useful life is very far into the
future.
-
Water: Pipes existed
for 10 years, and useful life 50-100 years.
|
|
Q: |
How long will it take
to move these pipes? |
|
A: |
Due to the permitting
process, 2-4 years for the reclaimed water pipes.
|
|
|
County Owned Utilities:
-
Potable water,
electrical, telephone and sewer.
-
Sewer: Gravity feed to
the lift station-a 4-inch pressure line. To move this inland, it
would cost from $150-300,000 (the higher cost if a new lift
station is required) if the line was moved offsite, this would
cost $450,000. This would require a bridge crossing and new lift
station.
-
Potable water
line-this is sub metered from the Airport. If rerouted inland 1100
feet, this would cost about $40,000.
-
To reroute the
electrical and telephone lines (900 lineal feet), would cost about
$50,000.
-
Total cost:
$240,000-540,000. This includes the cost of removal (or
abandonment-where lines would need to be removed)
|
|
|
|
6. |
Review of Areas of Agreement –
Development of Objectives: |
|
|
In order the guide discussion
regarding scenarios, it is important for the Working Group to agree on its
desired goal and objectives for the master planning process. A draft was
presented to the group, taken from comments at previous meetings. The group
agreed upon a revised set of objectives, to be distributed to the group
later in the week. A summary of the points discussed follows.
-
The goal statement focuses
on a 20-year time horizon because that is the County’s planning
horizon for projects. Include the balance of park and beach in the
goal statement.
-
There was a discussion
about what “park” means and so it was suggested to substitute Goleta
Beach Park, which includes the beach and the park.
-
“Sustainable” is
ambiguous. Is it very meaningful? The Board includes attainable and
sustainable in its discussions of goals for the Park.
-
Jeremy Lowe: Some guidance
is needed when defining long term-over 20 years. He suggested using
“works with natural processes” instead of sustainable. By including
natural processes-this includes the context of the environment such as
the slough, ocean, etc.
-
The goal statement should
not include “charged” words.
-
We need to recognize that
the park is a dynamic area.
|
|
|
7. |
Review of Conceptual
Alternatives |
|
|
Draft scenarios were distributed
to the group. These were developed by staff (Susan Rose’s office and Parks
Department) as a starting point for discussion, in the interest of saving
time at working group meetings. Jeremy Lowe has reviewed each scenario but
did not have time to suggest revisions or alterations. It is expected that
the scenarios will be revised by working group members and that new
scenarios may be created. Facilitator Lynn Rodriguez suggested that Jeremy
describe each scenario and help answer questions.
Terri Maus-Nisich, County Parks Director, commented that the scenarios
developed were broad based for Working Group members to begin discussions.
Not every scenario is presented. The four scenarios set forth are to put
something “on the table” and start discussion. There are no costs attached,
as we don’t want to limit the alternatives.
-
Variables that can change: Offshore
structures, kelp, parking, and ranger residence.
-
Constants in each scenaario: Beach
nourishment, repairs to existing revetment.
|
Scenarios
-
Hold the line: Rock
revetment all around the beach.
This doesn’t address erosion problems. It maintains real estate. It
doesn’t take into account dissipating ocean waves or undermining of
the revetment. Long-term maintenance is needed, with a constant cycle
of renourishment. This doesn’t stabilize the shoreline or the beach.
-
Managed retreat:
This gives the active beach more space in which to evolve. What shape
is the beach trying to be? What is the stable position of the beach?
Can this be accommodated with managed retreat? Don’t put structures
within “red line” area. This is limited by the amount of space; look
at ways of bringing the shoreline forward.
-
Extend escarpment:
(derived using variables)
Move the shoreline forward. Extend the length of the escarpment, and
prefill the area. This provides a stable hold for the shoreline to
build on. The length of the structure depends on how big of a beach
you want.
If the escarpment becomes a groin, the losses of sand lie on the other
side of the groin.
Offshore breakwater: The length and position of offshore structures
reduces wave energy and traps sediment. Pre-fill must also be done
with offshore breakwaters. This structure takes sediment out of the
littoral cell and has impacts down shore. This propagates the creation
of additional structures down shore.
Must allow for natural change to occur. This may include a combination
of structures and/or a reorganization of structures on land. It may
also require a change in uses.
-
East End Retreat
This allows natural process at the east end to take place. It includes
potential new parking areas, and relocating the east end parking. The
ranger station is being phased out and will be removed. In this area
maintenance shed or viewing area can take its place. This is a
tradeoff in landscaped areas for parking. It removes the need to
relocate utilities.
-
Variables
Other options utilizing a number of changing variables were discussed.
A list of suggestion “tools” or solutions was provided.
The Working Group was asked to consider all information, review
scenarios, and be prepared to thoughts for scenarios on March 18,
2004.
|
Concluding remarks:
-
What is a stable beach?
These questions will need to be addressed in alternatives in the EIR.
-
A naturalized headland
existed on the west end before the area eroded.
-
Inshore bathymetry is
needed.
|
|
|
8. |
Next meeting dates: |
|
|
March 18, 2:30 at the Airport
Administrative Building. The final meeting date(s) will be determined at the
next meeting. Spring break for local schools falls during the next regularly
scheduled meeting date.
|
|
|
|